|
A method for measuring progress on projects and indicating variances in planned accomplishments, schedule, and cost expenditures.
EVM, also called earned value analysis (EVA, not to be confused with economic value added) is primarily used as a way of reporting project progress to
stakeholders, and government regulations often require that contractors providing services to federal and other government agencies comply with standards for using EVM. In the context
of project portfolio management (PPM), EVM provides a method for reporting progress on individual projects and for demonstrating compliance with
government requirements for EVM.
The basic concept with EVM is that project work be planned, budgeted, and scheduled in time-phased, "planned value" increments. Typically, these work increments are
defined in a hierarchical fashion as a work breakdown structure, but for a smaller project the work elements might simply be individual project tasks.
The work elements define a schedule and cost/value baseline for the project. As project work is conducted, project value is "earned." Various indices are computed that summarize project
status based on comparing earned value with planned and actual costs.
The value that is assigned to each work element is termed its planned value (PV). The PV is meant to be a quantity or weighting factor that indicates the portion of
the project value that, according to the plan, will be contributed by that work element at a specified time. A work element's PV could be set equal to its cost, the number of labor
hours required, or a subjectively assigned number of "points."
The value of the work element is earned as the work is completed. For example, the earning rule might be that 25% of the value is earned when the task is started, and
the remaining 75% is earned upon completion.
Progress against the plan is reported on a regular basis (e.g., weekly or monthly) by accumulating earned value (EV) based on the earning rules. By subtracting the
value of the work planned (PV) from the value of the work performed (EV), a schedule variance (SV) may be computed at any point in time during the project:
SV = EV - PV.
(Some EVM documents alternatively define SV = PV - EV. With the definition given above, negative numbers are "unfavorable," and positive numbers are "favorable.")
Similarly, a schedule performance index (SPI) may be computed by dividing the EV by the PV:
SPI = EV/PV.
If the SV is greater than zero (SPI is greater than 1), the work is ahead of schedule. If the SV is less than zero (SPI is less than 1), the work is behind schedule.
Schedule variances can be rolled up to any level in the work breakdown schedule to provide higher-level indicators of schedule compliance.
Since a work element's PV is traditionally chosen to be the scheduled cost of the work, the traditional term for a work element's planned value is the budgeted cost
for work scheduled (BCWS). The traditional term for earned value is the budgeted cost for work performed (BCWP). The actual cost of conducting each work element is termed the actual
cost of work performed (ACWP). In this context, where value and cost are both measured in dollars, a cost variance (CV) can be computed by subtracting the actual cost of work performed
(ACWP) from the budgeted cost of work performed (BCWP):
CV = BCWP - ACWP = EV - AC.
EVM defines many additional indicators of technical, schedule, and cost performance that can also be calculated, and guidance is available for interpreting and
addressing the various discrepancies that the indicators may reveal. As you can no doubt appreciate, EVM can be confusing because of the many acronyms that are used.
Although EVM is a well-established and effective means for managing the completion of complex projects, it's major limitation from the standpoint of PPM is that it
does not provide indicators for tracking or updating the anticipated ability of the project to deliver benefits to the organization. EVM might, for example, indicate that a project is
under budget, ahead of schedule, and within scope, but that project could nevertheless be in trouble with regard to achieving the benefits that
motivated the decision to fund it.
|